1.1
00:00:00.000 --> 00:00:10.000
<v Speaker 1>A proof of concept is meant to answer a question. The trouble is that plenty of them run for weeks without anyone stating the question.

1.2
00:00:10.000 --> 00:00:16.800
<v Speaker 2>Then it ends, everyone feels vaguely positive, and the decision gets made on politics instead of evidence.

1.3
00:00:16.800 --> 00:00:26.400
<v Speaker 1>So the discipline is defining success criteria up front. What has to be true at the end for this to count as a pass?

1.4
00:00:26.400 --> 00:00:36.400
<v Speaker 2>Write it down, agree it with the vendor, and give it a deadline. A proof of concept without an end date becomes a free pilot.

2.1
00:00:36.400 --> 00:00:41.200
<v Speaker 1>How many times have you heard "it seemed great in the demo"?

2.2
00:00:41.200 --> 00:00:45.600
<v Speaker 2>Jumping straight into production with a new tool can be risky.

2.3
00:00:45.600 --> 00:00:52.000
<v Speaker 1>That's why teams run a proof of concept—to test the waters before committing budget and resources.

2.4
00:00:52.000 --> 00:00:58.800
<v Speaker 2>The goal is to validate that the vendor can solve the problem and fit into existing workflows.

2.5
00:00:58.800 --> 00:01:06.000
<v Speaker 1>We'll walk through setting success criteria, keeping scope tight and evaluating results so POCs lead to clear decisions.

3.1
00:01:06.000 --> 00:01:09.200
<v Speaker 1>Proofs of concept drift when success isn't defined.

3.2
00:01:09.200 --> 00:01:15.200
<v Speaker 2>Agree on measurable outcomes—page load times under three seconds or an 80% user satisfaction score.

3.3
00:01:15.200 --> 00:01:18.400
<v Speaker 1>Set a short checklist of must-haves and nice-to-haves.

3.4
00:01:18.400 --> 00:01:22.800
<v Speaker 2>Document the baseline so you can compare results after the trial.

4.1
00:01:22.800 --> 00:01:26.800
<v Speaker 1>Ever seen a two-week POC turn into a three-month mini-project?

4.2
00:01:26.800 --> 00:01:30.000
<v Speaker 2>Also known as "POC creep"—feature creep's expensive cousin.

4.3
00:01:30.000 --> 00:01:34.000
<v Speaker 1>Keep the scope tight with limited users, datasets and integrations.

4.4
00:01:34.000 --> 00:01:38.000
<v Speaker 2>Assign a project lead, vendor contact and schedule regular check-ins.

4.5
00:01:38.000 --> 00:01:43.600
<v Speaker 1>Set a modest budget and communicate progress to stakeholders so the trial doesn't sprawl.

5.1
00:01:43.600 --> 00:01:47.200
<v Speaker 1>When the trial ends, gather metrics and user feedback.

5.2
00:01:47.200 --> 00:01:52.800
<v Speaker 2>Compare the results against the success criteria—cost per user, integration complexity and training needs.

5.3
00:01:52.800 --> 00:01:56.000
<v Speaker 1>Decide whether to proceed, adjust or walk away.

5.4
00:01:56.000 --> 00:02:01.200
<v Speaker 2>Don't let the vendor drag things out hoping you'll forget the initial criteria.

5.5
00:02:01.200 --> 00:02:06.000
<v Speaker 1>Summarise the findings in a short report so stakeholders understand the recommendation.

6.1
00:02:06.000 --> 00:02:09.200
<v Speaker 1>Common pitfalls? Free trials that aren't really free.

6.2
00:02:09.200 --> 00:02:12.800
<v Speaker 2>Or testing with data that's nothing like real life.

6.3
00:02:12.800 --> 00:02:20.000
<v Speaker 1>Keep an eye out for POC creep and rein in vendors who keep adding "just one more feature."

6.4
00:02:20.000 --> 00:02:25.200
<v Speaker 2>Avoid these traps and you'll get a clear read on the solution's value.

7.1
00:02:25.200 --> 00:02:28.400
<v Speaker 1>To justify a POC, track what it costs.

7.2
00:02:28.400 --> 00:02:30.800
<v Speaker 2>Count staff time, licenses and infrastructure.

7.3
00:02:30.800 --> 00:02:34.400
<v Speaker 1>Then compare those costs to potential savings or revenue.

7.4
00:02:34.400 --> 00:02:38.800
<v Speaker 2>Share the math so stakeholders see whether the trial paid off.

8.1
00:02:38.800 --> 00:02:42.800
<v Speaker 1>Sometimes the best decision is to cut the trial short.

8.2
00:02:42.800 --> 00:02:47.600
<v Speaker 2>Define exit criteria upfront so you know when to pull the plug.

8.3
00:02:47.600 --> 00:02:51.200
<v Speaker 1>Communicate the decision quickly to stakeholders and the vendor.

8.4
00:02:51.200 --> 00:02:53.600
<v Speaker 2>Capture lessons learned and move on.

9.1
00:02:53.600 --> 00:02:58.800
<v Speaker 1>A good proof of concept either saves you money or makes you money.

9.2
00:02:58.800 --> 00:03:01.600
<v Speaker 2>A bad one does both—for the vendor.

9.3
00:03:01.600 --> 00:03:04.400
<v Speaker 1>Define success, control scope and evaluate honestly.

9.4
00:03:04.400 --> 00:03:09.600
<v Speaker 2>Then you can move forward with evidence or save money by walking away.

9.5
00:03:09.600 --> 00:03:11.600
<v Speaker 1>Either outcome beats committing blindly.